Home / EMEA / MODERNIZATION SIGNALLING-TELECOMMUNICATION SYSTEM along Railway line – Banja Luka- Doboj- and Sevarlije-Doboj-Samac

MODERNIZATION SIGNALLING-TELECOMMUNICATION SYSTEM along Railway line – Banja Luka- Doboj- and Sevarlije-Doboj-Samac

This Invitation for Tenders follows the General Procurement Notice for this project which was published in Procurement Opportunities on the EBRD website on 22 November 2013.

Bosnia and Herzegovina Railway Public Corporation- BHRPC and the Railway of Republika Srpska – ZRS (Project Implementation Unit –PIU) hereinafter referred to as the Purchaser, intends using part of the proceeds of a loan from the European Bank for Reconstruction and Development and European Investment Bank  (the Bank) towards the cost of:

Contract 1, Modernization signalling-telecommunication system along Railway line Banja Luka- Doboj- and Sevarlije-Doboj-Samac.

The Employer now invites sealed tenders from contractors for the following contract to be funded from part of the proceeds of the loan.

This Tender will be implemented in accordance with EBRD Procurement Policies and Rules May 2010.

* Projects along the line parallel to Corridor X consist of following:

• Interstation dependence system S.Kostajnica — until Banja Luka all included.

• Interlocking of the level crossing ‘Rasadnlk” at km 12+307 (located between the caution signal and the entry signal of the station Stanovi)

• Interlocking of the station Ostruznja, which contains the following:

– Station signalling devices with interstation dependence system (MZ) Stanovi Ostrunja

– Stanari, along with procurement and laying of cables for local telephony

– Electric point heating system

– Power supply system from the OCL and distribution network Low-voltage cable network and energetics

– Revitalization of the station building with adaptation of the technical rooms

– Rehabilitation of the station tracks (except  for the  running   track)  according to the requirements for installation of signalling devices

• Point heating system at the station Stanari

• Interlocking of the level crossing Kulasi at km 35+365 (located at the interstation distance Dragalovci –  Prisoje)

• Point heating system at the station Prisoje

• Interlocking of the station Snjegotina, which contains the following:

– Station signalling devices with interstation dependence system (MZ) Ukrina — Snjegotina — Josavka, along with procurement and laying of cables for local telephony

– Electric point heating system

– Power supply system from the OCL and distribution network

– Low voltage cable network and energetics

– Revitalization of the station building with adaptation of the technical rooms

– Rehabilitation  of  station  tracks  (except  for the  running   track) according to the requirements of installation of signalling devices

• Interlocking of the station Josavka, which contains the following:

– Station signalling devices with interstation dependence system (MZ) Snjegotina — Josavka — Celinac, along with procurement and laying of cables for local telephony

– Electric point heating system

– Power supply system from the OCL and distribution network

– Low-voltage cable network and energetics

– Interlocking of the station level crossing at kin 70+925

– Revitalization of the station building with adaptation of the technical rooms

– Rehabilitation of the station tracks (except  for the  running   track) according to the requirements for installation of signalling devices

• Interlocking of the station Celinac, which contains the following:

– Station signalling devices with interstation dependence system (MZ) Joavka — Celinac

Vrbanja, along with procurement and laying of cables for local telephony

–  Electric point heating system

– Power supply system from the OCL and distribution network

– Low-voltage cable network and energetics

– Interlocking of the station level crossing at kin 79+419

– Revitalization of the station building with adaptation of the technical rooms

– Rehabilitation of the station tracks (except  for the  running   track) according to the requirements for installation of signalling devices

• Interlocking of the station Vrbanja, which contains the following:

– Station signalling devices with interstation dependence  system (MZ) Celinac Vrbanja — Banja Luka, along with procurement and laying of cables for local telephony

– Electric point heating system

– Power supply system from the OCL and distribution network

– Low-voltage cable network and energeties

– Interlocking of the station level crossing at km 88+692

– Revitalization of the station building with adaptation of the technical rooms

– Rehabilitation of the station tracks (except  for the  running   track) according to the requirements for installation of signalling devices

• Interlocking of the station Banja Luka, which contains the following:

– Station signalling devices with interstation dependence system (MZ) Celinac — Vrbanja — Banja Luka, along with procurement and laying of cables for local telephony

– Electric point heating system

– Power supply system from the OCL and distribution network

– Low-voltage cable network and energetics

– Constructive adaptation of technical rooms

– Rehabilitation of the station tracks (except  for the  running   track) according to the requirements for installation of signalling devices

• Procurement and installation of external and internal telecommunication equipment with cable  and Optical Fiber Cable at the official points Sevarlije, Doboj, S.Kostajnica, Rudanka, Stanovi, Dragalovci, Ukrina, Snjegotina, Joavka, Celinac, Vrbanja and Banja Luka.

Projects along the Corridor Vc consist of following:

• Completion of the existing interlocking system at the station Samac

• Completion of the existing interlocking system at the station Modrica

• Completion of the existing interlocking system at the station Koprivna Gornja

 

• Interlocking of the station Sevarlije, which contains the following:

– Station signalling devices   with interstation dependence system Sevarlije

– Doboj on both tracks, along with procurement and laying of cables for local telephony

– Electric point heating system

– Power supply system from the OCL and distribution network

– Low-voltage cable network and energetics

– Revitalization of the station building with adaptation of the technical rooms

– Rehabilitation of the station tracks according to the requirements for installation of signalling devices

 

It is estimated that the Construction Contract will have duration of 12 Months plus Defect Notification Period of 12 months.

Tendering for contracts to be financed with the proceeds of a loan from the Bank is open to firms from any country. The proceeds of the Bank’s loan will not be used for the purpose of any payment to persons or entities, of for any import of goods, if such payment or import is prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations.

 

Check Also

Nokia's communications network to support railway operations on Malaysia's first mass rapid transit line

Nokia’s communications network to support railway operations on Malaysia’s first mass rapid transit line

Nokia has supplied a mission-critical communications network to LG CNS – a Korea-based systems integrator …

Leave a Reply

Your email address will not be published. Required fields are marked *